PAPAR: The construction of the Syariah Lower Court here involving an allocation of RM18.5mil is scheduled to be completed on Aug 25, 2024, says Datuk Armizan Mohd AliThe Minister in the Prime Minister’s Department said the project, approved under the third rolling plan of the 11th Malaysia Plan, was running smoothly, and the work progress is 7.98%, or six days, ahead of schedule.
“The site that has been identified is a swampy area which involved additional financial implications. Therefore, the federal government has approved an additional ceiling cost of RM3.5mil, and the latest value of the project is RM18.5mil,” he said in his speech after a visit to the project site here Saturday .
“Today’s visit is to see the progress of initial works and gather feedback on any arising issues,” he said.